7 Strip Surface Preparation Equipment
7.1 Installation of Shot Blaster
7.1.1 When adjusting the elevation and levelness,the surface of supporting roller should be taken as the datum point.
7.1.2 When adjusting the longitudinal and lateral central lines,the central line of box body should be taken as the datum point.